I messed up.

The last four weeks…

We spent the last four weeks burning branches, got the water hooked up, power installed:

This slideshow requires JavaScript.

Digging 31 holes and moving the driveway

I checked the weather for the second week of April – and noticed they were forecasting about a week’s worth of dry weather.

20170412_182827_zpstlj2py88

If you read my last post, you know it’s been raining every 2-3 days for a month or more. So this little break meant go time. I called the excavator- he said he could come Monday.

I busted my butt finishing up the last of the pier collars on Friday, but then the excavator called on Friday and asked if he could come Saturday instead- great! Except all the rain washed away my month old paint marks for where to dig the holes. So, Friday night, I loaded the trailer with the collars.

20170412_183208_zpsokdmtwxf

I left early Saturday morning to meet him out there at 8:30, and the trailer was fishtailing with all the collars on it. I didn’t know it at the time, but some of them had slipped a little after I tied them, and were hanging out the back of the trailer. It wasn’t many, but enough to shift the balance of weight. I took the drive very slowly- 20 mph, but it wasn’t enough- after fishtailing, the tongue of the trailer wore out and broke in half.

Looking at the tongue, I was surprised-  they used 1/8″ thick angle steel everywhere on the trailer except the tongue. On the tongue- the most important part of the trailer- they cheaped out and used 1/16″ square tube. I’ll never understand people. I could write a whole post on fixing the trailer, but let’s just give the short version: had to leave it on the highway, get my holes dug, then go back for the trailer. Used a blow torch to cut the hardened steel pivot bolt off the trailer side of the tongue. Brass welded the tongue back together at the neighbor’s house, hooked onto the trailer, and went to property to unload collars.

Then, the tongue broke again on the way back (empty). Stupid thing did a cartwheel on the highway. 5-6 good people stopped to help, and nobody got hurt. Met Matthew Hunter, who hooked me up with a new tongue and paint job on the trailer. Tongue is now 1/8″ x 4″x2″ tube steel- it’s a beast. And the trailer no longer tilts (I hated that “feature”), and pulls like a dream.

I got the holes dug- took him only two hours instead of four:

20170408_092806_zpsjlapisnj

and moved the driveway:

This slideshow requires JavaScript.

I also fixed a flat tire on the tractor

20170411_163522_zpsh4zduwq6

So, how did I mess up?

Details about the plans:

Capture

Above: You can see the detail of a corner of the pier layout:

  • red: pier outline
  • purple: outer edge of log walls
  • white: center of log wall

As you can see, the plans don’t specify a measurement or offset from the edge for where to place the logs on the piers- probably because they don’t know what size logs you will use- the plans state they are for 12″ logs, but mine are a little larger- like 18″ or something. Starting with what you know:

  • base of pier is 36″ square
  • top of pier is 8″x24″
  • log (according to the plans) is 12″ diameter
  • log is supposed to set just in from the edge of pier, not the center.

Thinking about the above brings up a practical question: How far from the bottom edge of the pier do you place the rebar (i.e. the white line goes over the top of each stick of rebar in each pier)? To ask another way, if I hang my string layout at 40’x40′ square, how far out from the string is the edge of each hole for each pier?

My mistake in laying out the foundation was that I never considered this. So I spray-painted marks where I thought they should go, but I can’t prove that is actually where they go. So I messed up.

This slideshow requires JavaScript.

I spent all day Wednesday burning in the hot sun to place 4 piers. I had to dig about 12″x36″x18″ of dirt to get the forms lined up correctly under the string. My wife finally talked me out of my stubbornness- and had me call the excavator. It took me five hours to fix 4 holes. I got better at it, but 31 holes means 31 hours of work if I do it by hand.  I did accomplish one thing: I know how far from the string the bottom edge of the pier goes- in my case, to get the rebar 8″ from the top edge, I need the bottom edge to be 16″ from the string. I got a plumb bob and a tape measure, and spray-painted marks. Then I called Jim to have the excavator come back and cut some more out of my holes. He couldn’t do it right away, but said he would call. I was worried he won’t get it done before the next rain, but he pulled off of a job he was doing on Cloud Trail road, came over to my place and fixed the gravel and the holes. He left before we showed up- under an hour.

Moving forward

Leveling the holes is now taking me about 10 minutes, instead of an hour. There’s a small chance of rain next week. Cross your fingers, and pray I can get concrete before anything happens.

Advertisements

Rain, Rain, go away

 

I need about a week of dry weather. Here’s the story:

Contacted my excavator- he still says he can dig 31 holes for about $400. He came out to look at my site on March 3, and said he can dig the holes any time I want, but he did  point out that I should have the plywood forms ready to drop in the holes the day he digs them. Which, at the time, I didn’t have any built, but I did have the plywood for them.

That sets up a few things that needed to happen:

Pour schedule

Day 0: foundation is dug, forms are ready to put in ground, rebar is onsite, and cut to size.

Day 1: level holes, install forms.

Day 2: Orient forms perfectly so the rebar will be ready to accept logs. The whole focus is to ensure the line of rebar sticking out of the tops of the piers is within 1/16″  perfectly lined up along the center of each line of piers along each side of the house. This helps with attaching the dreaded first layer of logs to the foundation, which is a pain, from what I hear.

Day 3: get pre-pour inspection done. Not sure what to expect here, but this is one of the inspections required by the city. I assume they are checking code to ensure piers are a minimum of 12″ below grade.

Day 4: pour concrete and place rebar in the forms.

Day 11:? pull plywood off forms. I think I wait a week after the pour to remove the plywood.
I have to do this over a short time period (think: days), because I think my forms (due to winter water damage) probably can’t take any more moisture. I don’t want them sitting around in the rain in holes in the ground while my rebar is on order, or while I try to get them oriented correctly. I just want to get them in the ground, orient them, get them inspected, and pour the concrete- preferably over the span of 2-3 dry days.

I did a final calculation on the volume of concrete needed. It’s a little tricky to calculate the volume of a “truncated regular pyramid”:

pyramid-11-638

Fortunately, the internet is a fantastic place for letting someone else do the heavy lifting, and there’s a website that will calculate the volume if you provide the a,b, & h. Turns out I need 0.66 cubic yards for each of my smaller forms (28), and 1.28 cubic yards for the larger forms (3), for a total of about 23 yards of concrete (about $2300).

This slideshow requires JavaScript.

Building the forms

I left the property after talking to Juni (the excavator) to go home and build forms. I built them all afternoon, and most of the next day (Saturday). Then I spent all week (when it wasn’t raining) building more. I almost finished building all 31 after a week of work. I need to put together the last three (which are the big ones- 54″x54″ base, 45 1/4″ tall).

My plywood was covered by a tarp all winter, but it still soaked up some water, which worries me. Concrete weighs about 3,700 pounds per cubic yard, and each pier is about 0.66 cubic yards, so I can figure about 2,400 pounds per pier. So the forms have to withstand 65 pounds per square foot (at least at the top). I also have to worry about the corners of the forms blowing out, or the bottoms, or maybe the whole pier will lift when the concrete is poured. I plan on using the extra dirt from the excavation to hold the forms down during the pour, and I’m adding collars to each one- found a cheap place (Mike’s Merchandise) to buy bolts – they sell surplus bolts and nuts for $1.00 per pound (13 nuts and bolts were a pound). I bought all they had in one size and ended up at about $20 of bolts- enough to do about 70% of the collars. If I had bought the same bolts at HomeDepot, it would have cost me $1.00 per bolt/nut, meaning, I would have paid about $372.00. So, my deal of $20-$30 is pretty cheap. Pays to shop around.

After building the forms, I have this huge pile of scrap leftover that I plan on using as part of the collars to strengthen the forms.

Getting Utilities installed

This has to be done before I can pass inspection- must have running water on site before you can pour concrete.

I went in January to get the utilities installed, but the utility company said I had to have a building permit. I went to the city to get the building permit, and they said I had to have utilities installed. Arggh! Will someone just please take my money so I can build?

I went back today, after getting the building permit- and they said, “Oh, do you have a copy of your building permit?” Well…..yes….posted out there on the property, like the city requires…. No matter- have to wait for the city electrical engineer to go out now (something else they didn’t mention last time….) and decide whether there’s enough power in the area to drop a line onto my property. She said she’ll take a picture of the permit while she’s out there tomorrow.

And I got the quote, too: normally, they come out and install a temporary utility pole with the meter on it. When you’re done building, you move the meter onto your house, and they come get the temporary pole. Of course, my build can’t be that simple, no- there’s no poles near my property – they are all across the street. So I have to pay for a permanent pole, plus a temporary pole (not sure why they can’t be the same). I also have to pay for a transformer. Expected cost: $5,000 for water, $385 for the temporary pole, and  $1800 for the permanent drop. Things are adding up…..

Sourcing Rebar

HomeDepot (hate to pick on them because they actually do sell 2×4’s for a good price, and they do have a lot of stuff in stock when you need it) sells rebar for about $0.50 per foot.

Capture

On the LHBA forum, there’s a section for posting “Craigslist finds”. On there, I discovered $0.30  per foot is a good deal. And just the other day, an advertisement popped up in my search:

Capture

I did the math- 7,000 ft for $1,000 works out to $0.14 per foot- a screaming deal. Except the guy (or gal, I guess), didn’t leave a phone number. Of course, 7,000 feet of rebar weighs 7,000 x .668 = 4676 lbs, so I’d need a bigger trailer (I think mine is rated for 2,000 pounds). But I only need 2600 feet for the cabin, and maybe half that for the garage. In the end, I could probably sell the scrap, and make my money back. In the end, the guy didn’t post any contact info- I pressed the “let poster know they didn’t leave any contact info” button. Several times. And again yesterday. And today. Twice. Maybe three times.

So I looked again for other ads, and found this guy in Decatur that says he’ll beat any price. I called him, and he did- $0.29 per foot. And he’ll cut it for free.  The old “a bird in the hand is better than two in the bush” holds true. And he spent all week last week cutting out plywood for forms for a house he’s building for himself. He wants the rain to go away, too…..

Summary

All of this adds up, of course, to a lot of money, time, and exhaustion. The main thing I’m worried about is that my forms don’t get left in the rain for days while I wait for an inspection, or the concrete, or the excavation. Getting all the materials, inspections, installations, and people lined up is quite an adventure. But once the foundation is done, the next adventure begins: getting ready to stack logs.

2016 July 24: Schedule for the rest of 2016

This slideshow requires JavaScript.

I got a little raise at work. Yay! Now, hopefully, our account will still be hundreds in the black instead of just tens a week before payday. It’s sort of self imposed: we committed to saving a small house payment-like amount when we started the build. We are counting on this amount to supplement our savings that we used to initially start things off. But I also have some student loan payments and we have the land loan every month, along with our utilities, groceries, gas, and the normal bills everyone has.

I’ve been worried about finances on the build for a few months now- the city charges $5,000 to hook up water, power, and sewer, and this amount will just about clean out our savings for the next few months, and make it difficult to get concrete poured (I’m thinking thousands for the concrete). But we can’t get a building permit until we have utilities, so it was becoming a roadblock to progress. With my little raise at work, we now have some breathing room on our build, although we won’t be able to do the concrete right away.

I’m still cleaning up tree debris from cutting twelve trees a few weeks ago- not ready to move logs, but hope to do so later this week. And the debris piles are getting huge. Even with saving the bigger branches, things are still piling up. I’m probably going to end up with ten or more debris piles. There is currently an annual “burn ban” for the summer in the county we live in, so no burning until October. And I think I’ll be required to have running water on hand while burning brush.

This slideshow requires JavaScript.

 

I also need to borate the trees I have. Borating the trees stops mold and bugs (mostly termites) from setting up shop in your house. Borating only really needs to be done once if your logs are already stacked and dried in (protected from rain). My logs are laying around exposed to the elements, so I’m going to have to treat them twice- once now, and once again when they are under roof. Once they are under roof, further borating is not necessary. The boric acid discourages insects, while the glycol causes the tree to suck up the solution much farther than just water would do. For LHBA members (password and membership required), I like the thread “NOTICE – Borate Mixture- Notice” under the “log home construction” folder. Three ingredients- borax, boric acid, and some kind of glycol. There are some surface mold spots on the logs I’ve peeled (thank you,  ‘The South’, and your overly humid weather). I bought a metal bushel, but I still have to buy the borax and the glycol (both available at Walmart). I also have a sprayer (thank you, Harbor Freight, for having extremely cheap tools). Just need a few hours to boil up some brew…

This slideshow requires JavaScript.

All of the above has caused me to think about a (very aggressive) build schedule for the rest of the year:

  • July
    • continue to cut trees, clean up brush.
    • Hope to end the month with 18 existing + 15 new = 33 trees on racks, and half of them peeled.
    • borate the trees I’ve peeled.
  • August
    • cut and haul more trees- hopefully, by end of August, get 20 more trees for a total of 53 trees- enough to start the build. I think I only need 48 for the walls, but I want some breathing room. I also still need a bunch for the roof purlins, lifting logs, cap logs, ridge poles, etc, but I can at least get the build going once I have the minimum.
  • September
    • Peel all trees, and borate the remainder once peeled.
  • October
    • pay for water hook up
    • submit plans and get building permit
    • dig and pour foundation
  • November
    • lay first logs for walls. This also means I’ll make this blog public- that is the goal- make it public after the first few courses of logs are laid.
    • burn brush piles and maybe stumps
  • December
    • Lay last log for walls
  • January 2017 (or whenever I have funds)
    • Get the freakin’ roof on!

At some point, I need to get more tools and materials. Items I’m still missing:

  • plywood for foundation forms ($200)
  • concrete ($2400)
  • rebar (about $1200)
  • 2 3-ton chain hoists ($160)
  • rebar cutter ($150) or chop saw blades ($50?)
  • styrofoam for roof (I don’t know- probably $200-500)
  • roof panels (probably metal roof – $3000)
  • T&G roof decking ($2000)
  • plywood roof underlayment (I don’t know)

It’s obviously very ambitious for one person, not to mention one person that has never done this before. I’m sure there will be delays due to finances or hassles with the city, equipment breakdowns, etc. But if the schedule needs to be adjusted by two or three months, that’s ok- I need to wait for a tax return for a boost to my finances anyway.  It still appears that I can “git-r-dun” within my goal of 2-3 years.